BEFORE THE INSTALLATION, THESE MATTERS NEED ATTENTION
1. The product should be put down gently.
2. Installations in acid and alkaline environment is not recommended.
3. The product must be grounded.
4. The products are required to check the product brand mark on the voltage and the local voltage whether conform.
5. Ensure the power rating should have sufficient current carrying capacity.
6. The possible danger of installation close to curtains and other combustible materials.
ENSURE THE PRODUCTION’S INSTALLATION SITE
For the safe use of the product, the product installation position should guarantee the bottom minimum height of 1.8 m from the ground. Ceiling or other coverings minimum distance is 0.5 m, minimum distance with both sides wall is 0.5 m (as shown in figure 1).

INSTALLATION STEPS
![]() |
Step 1: According to the product installation location, use percussion drilling to make three diameter 8 mm round holes |
![]() |
Step 2: Insert the three plastic wall anchors to the three holes |
![]() |
Step 3: Mount the bracket by three ST4*35 screws and make sure the installation points are secured. For mounting on concrete use two previous points prior to this point. For mounting on wood surface use only this point. For any mounting surface be sure to check that the bracket is securely mounted. |
![]() |
Step 4: Before fixed the heater, make sure the rocker power switch on the right side and then fixed the bracket and heater by two M6*14 screws and butterfly nuts |